#14

 

 

 

Mgmt 380

 

Assignment #9

15 points

DUE:  Thursday, November 30

 

 

 

Examine problem 36 on page 318 in your textbook.

 

1.   Draw the network.  Label each activity (with a letter) and each milestone (with a number). 

 

2.      Construct a chart that determines the critical path and calculates the project duration.

 

3.      Compute the probability that the student union can complete the arrangements within 30 days.

 

4.      Compute the probability that the student union can complete the arrangements in 20 days.